Standard Cited: 19260416 A03 General requirements.
Inspection Nr: 1285080.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $3,880.00
Current Penalty: $2,910.00
Issuance Date: 06/12/2018
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC): A
Gravity: 10
Report ID: 0626700
Contest Date:
Final Order: 07/10/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/10/2018 | $2,910.00 | Serious | ||
Penalty | Z: Issued | 06/12/2018 | $3,880.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.416(a)(3): Before work began, the employer did not ascertain by inquiry, direct observation, or by instruments, whether any part of an energized electric power circuit, exposed or concealed, was so located that the performance of the work could bring any person, tool, or machine into physical or electrical contact with the electric power circuit: a) On or about December 19, 2017, prior to work beginning, the employer did not ascertain if any part of an energized electric power circuit was so located that it could be contacted by an employee.