Violation Detail
Standard Cited: 19260451 B05 II General requirements.
Inspection Nr: 1285031.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $3,326.00
Current Penalty: $2,330.00
Issuance Date: 01/11/2018
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity: 5
Report ID: 0111500
Contest Date:
Final Order: 02/06/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 02/06/2018 | $2,330.00 | Serious | ||
Penalty | Z: Issued | 01/11/2018 | $3,326.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(b)(5)(ii): The end of a platform greater than 10 feet in length extended over its support more than 18 inches and the platform was not designed and installed so that the cantilevered portion of the platform is able to support employees without tipping, or has guardrails which block employee access to the cantilivered end. Worksite: The employer did not ensure that the pump jack scaffold from that employees were required to work was installed properly so that the cantilevered portion of the platform was able support employees without tipping, or had guardrails which blocked employee access to the cantilevered end.