Standard Cited: 19100269 D02 IV B Electric Power Generation, Transmission, and Distribution.
Inspection Nr: 1283622.015
Citation: 01001
Citation Type: Serious
Abatement Date: 06/15/2018 7
Initial Penalty: $12,934.00
Current Penalty: $12,934.00
Issuance Date: 05/21/2018
Nr Instances: 1
Nr Exposed: 5
Related Event Code (REC): R
Gravity: 10
Report ID: 0420100
Contest Date: 06/15/2018
Final Order: 05/06/2021
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 05/06/2021 | $12,934.00 | 06/15/2018 | Serious | |
Penalty | C: Contested | 06/19/2018 | $12,934.00 | 06/15/2018 | Serious | |
Penalty | Z: Issued | 05/21/2018 | $12,934.00 | 06/15/2018 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(d)(2)(iv)(B): Specific procedural steps for shutting down, isolating, blocking and securing machines or equipment to control hazardous energy; (a) Rail Yard - On or about December 10, 2017 the employers written Lock Out/Tag Out Program did not clearly and specifically outline the procedures to be utilized for controlling the pneumatic energy on the rail cars during cleaning of coal spills along the incoming rail tracks leading to the dump pit.