Violation Detail
Standard Cited: 19260752 C02 Site layout, site-specific erection plan and construction sequence.
Inspection Nr: 1280987.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $12,934.00
Current Penalty: $9,000.00
Issuance Date: 05/23/2018
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0215600
Contest Date:
Final Order: 06/14/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 06/14/2018 | $9,000.00 | Serious | ||
Penalty | Z: Issued | 05/23/2018 | $12,934.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.752(c)(2): The controlling contractor did not ensure that a firm, properly graded, drained area, readily accessible to the work with adequate space for the safe storage of materials and the safe operation of the erector's equipment: A). On or about 12/05/2017, at North west side of Head House La Guardia Airport Terminal B. Flushing, NY I-beams stored on the ground for steel erection were not level. One of the I-beams was rolled over and injured an employee's leg. ABATEMENT VERIFICATION IS NOT REQUIRED PURSUANT TO 29 CFR 1903.19.