Violation Detail
Standard Cited: 19260451 E01 General requirements.
Inspection Nr: 1258842.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $5,174.00
Current Penalty: $5,174.00
Issuance Date: 02/21/2018
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 03/08/2018
Gravity: 5
Report ID: 0316100
Contest Date:
Final Order: 03/19/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 03/19/2018 | $5,174.00 | 03/08/2018 | Serious | |
| Penalty | Z: Issued | 02/21/2018 | $5,174.00 | 03/08/2018 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(e)(1): When scaffold platforms were more than 2 feet (0.6 m) above or below a point of access, portable ladders, hook-on ladders, attachable ladders, stair towers (scaffold stairways/towers), stairway-type ladders (such as ladder stands), ramps, walkways, integral prefabricated scaffold access, or direct access from other scaffold, structure, personnel hoist, or similar surface was not used: a) Tenth Floor, Multi-point suspension Scaffold - On or about August, 24, 2017, water proofers had to climb from the building's 10th floor up 44 inches onto the lower platform since a safe means to access the scaffold's platform was not provided. In accordance with 29 CFR 1903.19(d), abatement certification is required for this violation (using the Certification of Corrective Action Worksheet).