Standard Cited: 19100269 L01 III Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1243552.015
Citation: 01001
Citation Type: Serious
Abatement Status:
Initial Penalty: $12,675.00
Current Penalty: $0.00
Issuance Date: 12/19/2017
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 12/26/2017
Gravity: 10
Report ID: 0317000
Contest Date: 01/18/2018
Final Order: 03/26/2018
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 03/26/2018 | $0.00 | 12/26/2017 | Serious | |
| Penalty | C: Contested | 02/13/2018 | $12,675.00 | 12/26/2017 | Serious | |
| Penalty | Z: Issued | 12/19/2017 | $12,675.00 | 12/26/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(l)(1)(iii): Electric lines and equipment were not considered and treated as energized or had otherwise been deenergized in accordance with paragraph (d) or (m) of this section: a) Jobsite: PECO Pole# 2802 - The employer did not ensure an employee repairing an energized, downed 13.2 kv primary line treated the primary line as energized prior to working on it. Noted on or about 6/21/17.