Violation Detail
Standard Cited: 19100147 C04 II The control of hazardous energy (lockout/tagout).
Inspection Nr: 1232135.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $12,548.00
Current Penalty: $0.00
Issuance Date: 11/09/2017
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 01/12/2018
Gravity:
Report ID: 0524530
Contest Date:
Final Order: 12/01/2017
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 12/01/2017 | $0.00 | 01/12/2018 | Other | |
Penalty | Z: Issued | 11/09/2017 | $12,548.00 | 12/07/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii): The energy control procedures did not clearly and specifically outline the scope, purpose, authorization, rules, and techniques to be utilized for the control of hazardous energy, including, but not limited to Items of this section: The employer did not ensure that energy control procedures for the CNC Router machines specifically outlined the techniques to be utilized for the control of hazardous energy. The procedures were not updated to reflect the current machine location in the new shop and steps for shutting down, isolating, blocking and securing machines to control hazardous energy.