Violation Detail
Standard Cited: 19260850 C Preparatory operations.
Inspection Nr: 1221497.015
Citation: 01001
Citation Type: Serious
Abatement Date: 09/13/2017 2
Initial Penalty: $3,803.00
Current Penalty: $3,000.00
Issuance Date: 08/24/2017
Nr Instances: 1
Nr Exposed: 6
Related Event Code (REC): A
Gravity: 10
Report ID: 0627500
Contest Date:
Final Order: 09/06/2017
Emphasis:
Substance: 8870
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 09/06/2017 | $3,000.00 | 09/13/2017 | Serious | |
Penalty | Z: Issued | 08/24/2017 | $3,803.00 | 09/13/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.850(c): All electric, gas, water, steam, sewer, and other service lines were not shut off, capped, and/or otherwise controlled, outside the building line before demolition work was started. On or about March 29, 2017, the employer did not ensure that all utilities were shut off, capped, and/or otherwise controlled, outside the building before demolition work was started. The electric utility company was not notified in advance. This condition exposed employees to electrical shock hazards.