Violation Detail
Standard Cited: 19100147 C04 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1212247.015
Citation: 01001
Citation Type: Serious
Abatement Date: 04/20/2018 2
Initial Penalty: $8,873.00
Current Penalty: $8,873.00
Issuance Date: 04/14/2017
Nr Instances: 1
Nr Exposed: 1
Related Event Code (REC):
Gravity: 10
Report ID: 0111100
Contest Date: 05/08/2017
Final Order: 02/19/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | J: ALJ Decision | 02/19/2018 | $8,873.00 | 04/20/2018 | Serious | |
Penalty | C: Contested | 05/11/2017 | $8,873.00 | 05/10/2017 | Serious | |
Penalty | Z: Issued | 04/14/2017 | $8,873.00 | 05/10/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(i): Procedures were not developed, documented and utilized for the control of potentially hazardous energy when employees were engaged in activities covered by this section. Production heavy fabrication area - Energy control procedures for the roll grinding machine were not developed, documented or utilized to control potential hazardous energy when employees perform maintenance operations on the equipment.