Violation Detail
Standard Cited: 19100036 D01 Design and construction requirements for exit routes.
Inspection Nr: 1205721.015
Citation: 01001
Citation Type: Serious
Abatement Date: 07/14/2017 2
Initial Penalty: $6,338.00
Current Penalty: $3,169.00
Issuance Date: 06/19/2017
Nr Instances: 1
Nr Exposed: 40
Related Event Code (REC): C
Gravity: 5
Report ID: 0418800
Contest Date:
Final Order: 07/14/2017
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/14/2017 | $3,169.00 | 07/14/2017 | Serious | |
Penalty | Z: Issued | 06/19/2017 | $6,338.00 | 07/14/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.36(d)(1): Employee(s) were not able to open an exit route door from the inside at all times without keys, tools, or special knowledge: On or about January 26, 2017, at the above addressed worksite, the employer allowed its employees to work at a jobsite where all designated Exit doors had either a lock system to unlock the door before opening and/or had extra locked steel security doors and/or a security code was needed to exit; exposing employees to smoke inhalation, burns and possible death.