Standard Cited: 19100269 C04 II A Electric Power Generation, Transmission, and Distribution.
This violation item has been deleted.
Inspection Nr: 1171664.015
Citation: 01001
Citation Type: Serious
Abatement Date: 02/21/2017
Initial Penalty: $12,675.00
Current Penalty: $0.00
Issuance Date: 02/14/2017
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): A
Gravity: 10
Report ID: 0626700
Contest Date: 02/27/2017
Final Order: 02/01/2018
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 02/01/2018 | $0.00 | 02/21/2017 | Serious | |
Penalty | C: Contested | 03/02/2017 | $12,675.00 | 02/21/2017 | Serious | |
Penalty | Z: Issued | 02/14/2017 | $12,675.00 | 02/21/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.269(c)(4)(ii)(A): The employer did not conduct a more extensive discussion during the job briefing when the work was complicated or particularly hazardous: a) At the site, a more extensive discussion was not conducted during the job briefing when work was complicated by a road crossing which made the task particularly hazardous, exposing employees electrical hazards.