Violation Detail
Standard Cited: 19100119 C01 Process safety management of highly hazardous chemicals.
Inspection Nr: 1167966.015
Citation: 01001
Citation Type: Serious
Abatement Status: Abatement Completed
Initial Penalty: $8,730.00
Current Penalty: $6,250.00
Issuance Date: 12/27/2016
Nr Instances: 1
Nr Exposed: 12
Abatement Date: 02/09/2019
Gravity: 10
Report ID: 0214200
Contest Date:
Final Order: 01/19/2017
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/19/2017 | $6,250.00 | 02/09/2019 | Serious | |
| Penalty | Z: Issued | 12/27/2016 | $8,730.00 | 02/09/2017 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.119(c)(1): The employer did not develop a written plan of action regarding the implementation of the employee participation required by 29 CFR 1910.119: a) Building 3 - alkyd resin process for 537-50X The employer's written plan of action for employee participation in process safety management did not include the alkyd resin process. On 6/29/16 the company made an 11,699 pound batch of 537-50X, a flammable liquid with a flash point of 78 F. Violation occurred on or about 6/29/16.
Translate