Violation Detail
Standard Cited: 19100147 C04 II D The control of hazardous energy (lockout/tagout).
Inspection Nr: 1153887.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $4,500.00
Issuance Date: 07/26/2016
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 08/19/2016
Gravity:
Report ID: 0524500
Contest Date: 08/31/2016
Final Order: 01/05/2017
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 01/05/2017 | $4,500.00 | 08/19/2016 | Other | |
| Penalty | C: Contested | 09/01/2016 | $7,000.00 | 08/19/2016 | Serious | |
| Penalty | Z: Issued | 07/26/2016 | $7,000.00 | 08/19/2016 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(4)(ii)(D): The energy control procedures did not clearly and specifically outline the requirements for testing a machine or equipment to determine and verify the effectiveness of lockout devices, tagout devices, and other energy control: On or about May 18, 2016, employees performed maintenance activities on the Unit 12 South Gas Fan and the employer did not ensure the energy control procedures clearly documented and described the requirements for verifying the electrical energy and residual energy of the mechanical parts of the fan had been controlled.