Standard Cited: 19100119 H03 IV Process safety management of highly hazardous chemicals.
Inspection Nr: 1070025.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $7,000.00
Current Penalty: $7,000.00
Issuance Date: 12/09/2015
Nr Instances: 1
Nr Exposed: 6
Abatement Date: 12/31/2015
Gravity:
Report ID: 0626000
Contest Date: 12/29/2015
Final Order: 08/31/2016
Related Event Code (REC): A
Emphasis:
Substance: 1440
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 08/31/2016 | $7,000.00 | 12/31/2015 | Other | |
| Penalty | C: Contested | 02/04/2016 | $7,000.00 | 12/31/2015 | Serious | |
| Penalty | Z: Issued | 12/09/2015 | $7,000.00 | 12/31/2015 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.119(h)(3)(iv): The contract employer did not assure that each contract employee followed the safety rules of the facility including the safe work practices required by paragraph (f)(4) of this section: On June 10, 2015, at the Heads Column, DA-0501 at the INEOS Nitriles Green Lake Facility, the employer's implementation of the host employer's Opening Lines procedure, relating to hazardous chemicals in process piping, did not fully recognize the potential hazard to the operation.