Standard Cited: 19100219 C04 I Mechanical power-transmission apparatus.
This violation item has been deleted.
Inspection Nr: 1059865.015
Citation: 01001
Citation Type: Serious
Abatement Status: Quick Fix
Initial Penalty: $5,100.00
Current Penalty: $0.00
Issuance Date: 10/08/2015
Nr Instances: 1
Nr Exposed: 3
Abatement Date:
Gravity: 5
Report ID: 0418400
Contest Date: 11/03/2015
Final Order: 06/06/2016
Related Event Code (REC):
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | F: Formal Settlement | 06/06/2016 | $0.00 | Serious | ||
Penalty | C: Contested | 11/05/2015 | $5,100.00 | Serious | ||
Penalty | Z: Issued | 10/08/2015 | $5,100.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.219(c)(4)(i): Shaft ends projecting more than one-half the diameter of the shaft were not guarded by nonrotating caps or safety sleeves. a). Saw Mill - On or about and times prior to April 29, 2015, there was a projecting shaft end on the trim saw infeed conveyor system that was not guarded, thus exposing employees to a caught-in hazard.