Violation Detail
Standard Cited: 19100147 E02 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1057271.015
Citation: 01001
Citation Type: Serious
Abatement Status: Corrected During Inspection
Initial Penalty: $7,000.00
Current Penalty: $5,250.00
Issuance Date: 06/19/2015
Nr Instances: 1
Nr Exposed: 1
Abatement Date:
Gravity: 10
Report ID: 0213900
Contest Date:
Final Order: 07/17/2015
Related Event Code (REC): R
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 07/17/2015 | $5,250.00 | Serious | ||
| Penalty | Z: Issued | 06/19/2015 | $7,000.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(e)(2)(i): Before lockout or tagout devices were removed and energy was restored to the machine or equipment, authorized employees did not ensure that all employees had been safely positioned or removed from the work area: a) Salem Unit 2 Turbine Bldg. - Before removing tags and restoring power, authorized employees did not ensure that employees working in the Circ. Water Pump House were safely positioned. Employees in the Circ. Water Pump House were exposed to an electrical shock hazard. On or about 02/10/2015. NOTE: THE EMPLOYER IS REQUIRED TO SUBMIT ABATEMENT CERTIFICATION FOR THIS ITEM. FAILURE TO COMPLY WILL RESULT IN AN ADDITIONAL PENALTY OF $1000.00 IN ACCORDANCE WITH 29 CFR 1903.19.