Violation Detail
Standard Cited: 19100147 C06 I The control of hazardous energy (lockout/tagout).
Inspection Nr: 1055398.015
Citation: 01001
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $7,000.00
Current Penalty: $5,950.00
Issuance Date: 07/08/2015
Nr Instances: 1
Nr Exposed: 12
Related Event Code (REC):
Gravity: 10
Report ID: 0419700
Contest Date:
Final Order: 07/17/2015
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | I: Informal Settlement | 07/17/2015 | $5,950.00 | Serious | ||
Penalty | Z: Issued | 07/08/2015 | $7,000.00 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1910.147(c)(6)(i): The employer did not conduct a periodic inspection of the energy control procedure at least annually to ensure that the procedure and the requirement of this standard were being followed: a. On or about April 14, 2015, the employer did not conduct the periodic inspection of their energy control program since 2004.