Violation Detail
Standard Cited: 19260451 F03 General requirements.
Inspection Nr: 1053333.015
Citation: 01001
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $2,800.00
Current Penalty: $2,800.00
Issuance Date: 04/22/2015
Nr Instances: 1
Nr Exposed: 1
Abatement Date: 05/04/2015
Gravity: 10
Report ID: 0418600
Contest Date:
Final Order: 06/19/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 04/22/2015 | $2,800.00 | 05/04/2015 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(f)(3): Scaffolds and scaffold components were not inspected for visible defects by a competent person before each work shift, and after any occurrence which could affect a scaffold's structural integrity: a) At Lot 40 East Lake, Auburn, Alabama: On or about April 8, 2015 and at times prior; the employer failed to inspect scaffolding prior to use and allowed the co-owner to tie off to an anchor point which was not installed as per the manufactures recommendations exposing the employee to a fall hazard of in excess of 25 feet to the concrete floor below.