Violation Detail
Standard Cited: 19260025 A Housekeeping.
Inspection Nr: 1021105.015
Citation: 01001
Citation Type: Other
Abatement Status: Abatement Completed
Initial Penalty: $6,600.00
Current Penalty: $7,000.00
Issuance Date: 07/23/2015
Nr Instances: 3
Nr Exposed: 7
Abatement Date: 08/04/2015
Gravity:
Report ID: 0418800
Contest Date: 08/06/2015
Final Order: 01/29/2016
Related Event Code (REC): R
Emphasis:
Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
---|---|---|---|---|---|---|
Penalty | R: Review Commission | 01/29/2016 | $7,000.00 | 08/04/2015 | Other | |
Penalty | C: Contested | 09/17/2015 | $6,600.00 | 08/04/2015 | Serious | |
Penalty | Z: Issued | 07/23/2015 | $6,600.00 | 08/04/2015 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.25(a): During the course of construction, alteration, or repairs, debris was not kept cleared from work areas, passageways, and stairs, in and around buildings or other structures: a) On or about 01/27/2015, at the above addressed worksite, construction debris, ropes, rebar rods, garbage, sheets of plywood and pieces of lumber were strewn along the edge of the pier wall where the employees were working exposing them to fall hazards. b) On or about 01/28/2015, at the above addressed worksite, construction debris, ropes, rebar rods, garbage, sheets of plywood and pieces of lumber were strewn along the edge of the pier wall where the employees were working exposing them to fall hazards. c) On or about 02/05/2015, at the above addressed worksite, construction debris, ropes, rebar rods, garbage, sheets of plywood and pieces of lumber were strewn along the edge of the pier wall where the employees were working exposing them to fall hazards.