Violation Detail
Standard Cited: 19260451 F06 General requirements.
Inspection Nr: 1007087.015
Citation: 01001
Citation Type: Serious
Abatement Status: Not Completed - Worksite Changed
Initial Penalty: $2,800.00
Current Penalty: $2,800.00
Issuance Date: 12/18/2014
Nr Instances: 1
Nr Exposed: 2
Abatement Date: 12/28/2014
Gravity: 10
Report ID: 0215800
Contest Date:
Final Order: 01/22/2015
Related Event Code (REC):
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | Z: Issued | 12/18/2014 | $2,800.00 | 12/28/2014 | Serious |
Text For Citation: 01 Item/Group: 001 Hazard:
29 CFR 1926.451(f)(6): Scaffolds were erected, used, dismantled, altered, or moved such that they, or any conductive material handled on them, could have come closer than the minimum distances established for specific voltages as set forth in the table in subparagraph (f)(6).Note: Specify distances as indicated in table in paragraph (f)(6) of this section. a) At the jobsite, on or about 10/2/14: Employees assisted in the assembly of a ladder jack scaffold in close proximity (approximately 1 foot) to un-insulated supply power lines. Abatement certification must be submitted for this item.
Translate