Inspection Detail
Inspection: 316121722 - Zayo Fiber Solutions
Inspection Information - Office: Miosha Construction Safety & Health Division
Site Address:
Zayo Fiber Solutions
4723 Grand River
Lansing, MI 48906
Mailing Address:
737 Filley St, Lansing, MI 48906
Union Status: NonUnion
SIC:1731
NAICS: 238210/Electrical Contractors
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 10/12/2012
Planning Guide: Safety-Construction
Emphasis: S:Construction
Case Closed: 04/25/2013
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 3 | 6 | 9 | |||
| Current Violations | 3 | 6 | 9 | |||
| Initial Penalty | $4,200 | $0 | $0 | $0 | $0 | $4,200 |
| Current Penalty | $4,200 | $0 | $0 | $0 | $0 | $4,200 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19100268 B07 | 12/05/2012 | 12/10/2012 | $1,400 | $1,400 | $0 | - | ||
| 2. | 01002 | Serious | 19100268 I01 | 12/05/2012 | 12/10/2012 | $1,400 | $1,400 | $0 | - | ||
| 3. | 01003 | Serious | 4084321401 | 12/05/2012 | 12/10/2012 | $1,400 | $1,400 | $0 | - | ||
| 4. | 02001 | Other | 4084011401 | 12/05/2012 | 12/10/2012 | $0 | $0 | $0 | - | ||
| 5. | 02002 | Other | 40841721 | 12/05/2012 | 12/10/2012 | $0 | $0 | $0 | - | ||
| 6. | 02003 | Other | 40843206 | 12/05/2012 | 12/10/2012 | $0 | $0 | $0 | - | ||
| 7. | 02004 | Other | 4084320701 | 12/05/2012 | 12/10/2012 | $0 | $0 | $0 | - | ||
| 8. | 02005 | Other | 4084320708 | 12/05/2012 | 12/10/2012 | $0 | $0 | $0 | - | ||
| 9. | 02006 | Other | 4084320709 | 12/05/2012 | 12/10/2012 | $0 | $0 | $0 | - |