Inspection Detail
Inspection: 316044494 - Weld-Done Construction, Ltd
Inspection Information - Office: Fort Worth Area Office
Site Address:
Weld-Done Construction, Ltd
5405 Pleasant Run
Colleyville, TX 76034
Mailing Address:
1220 E. Highway 199, Springtown, TX 76082
Union Status: NonUnion
SIC:1791
NAICS: 238120/Structural Steel and Precast Concrete Contractors
Inspection Type: Planned
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 12/22/2011
Emphasis: L:Constr6
Case Closed: 04/17/2013
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 6 | 6 | ||||
| Current Violations | 6 | 6 | ||||
| Initial Penalty | $18,000 | $0 | $0 | $0 | $0 | $18,000 |
| Current Penalty | $8,910 | $0 | $0 | $0 | $0 | $8,910 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260100 A | 03/05/2012 | 03/08/2012 | $990 | $1,800 | $0 | I - Informal Settlement | ||
| 2. | 01002 | Serious | 19260404 F06 | 03/05/2012 | 03/15/2012 | $1,155 | $2,100 | $0 | I - Informal Settlement | ||
| 3. | 01003 | Serious | 19260416 E01 | 03/05/2012 | 03/15/2012 | $1,155 | $2,100 | $0 | I - Informal Settlement | ||
| 4. | 01004 | Serious | 19260501 B10 | 03/05/2012 | 03/22/2012 | $1,320 | $4,200 | $0 | I - Informal Settlement | ||
| 5. | 01005 | Serious | 19260602 C01 VI | 03/05/2012 | 03/22/2012 | $2,310 | $4,200 | $0 | I - Informal Settlement | ||
| 6. | 01006 | Serious | 19261053 B01 | 03/05/2012 | 03/15/2012 | $1,980 | $3,600 | $0 | I - Informal Settlement |
Translate