Inspection: 314531641 - Mark Rubel Construction
Inspection Information - Office: Sacramento District Office
Site Address:
Mark Rubel Construction
2437 Ahern St
Marysville, CA 95901
Mailing Address:
2394 Hwy 20, Marysville, CA 95901
Union Status: NonUnion
SIC:1771
NAICS: 238110/Poured Concrete Foundation and Structure Contractors
Inspection Type: Planned
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 09/03/2010
Planning Guide: Safety-Construction
Emphasis: S:Construction (Cship)
Case Closed: 06/28/2016
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | ||||
| Current Violations | 2 | 2 | ||||
| Initial Penalty | $0 | $0 | $0 | $260 | $0 | $260 |
| Current Penalty | $0 | $0 | $0 | $260 | $0 | $260 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 1509 A | 09/09/2010 | 09/14/2010 | $130 | $130 | $0 | 10/18/2010 | F - Formal Settlement | |
| 2. | 01002 | Other | 1509 C | 09/09/2010 | 09/14/2010 | $130 | $130 | $0 | 10/18/2010 | F - Formal Settlement |