Inspection Detail
Inspection: 314314998 - W Construction
Inspection Information - Office: Billings Area Office
Site Address:
W Construction
Corner Of West Cameron And North Weaver
Belgrade, MT 59714
Mailing Address:
214 South Willson Ave., Ste B, Bozeman, MT 59715
Union Status: NonUnion
SIC:1623
NAICS: 237110/Water and Sewer Line and Related Structures Construction
Inspection Type: Complaint
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 09/21/2010
Emphasis: N:Trench, S:Commercial Constr, S:Trenching
Case Closed: 06/27/2012
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Complaint | 207766239 | Yes | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 1 | 2 | |||
| Current Violations | 1 | 1 | 2 | |||
| Initial Penalty | $2,800 | $28,000 | $0 | $0 | $0 | $30,800 |
| Current Penalty | $0 | $14,000 | $0 | $1,400 | $0 | $15,400 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Other | 19260651 K02 | 03/07/2011 | 10/10/2011 | $1,400 | $2,800 | $0 | 03/22/2011 | F - Formal Settlement | |
| 2. | 02001 | Willful | 19260652 A01 | 03/07/2011 | 10/10/2011 | $14,000 | $28,000 | $0 | 03/22/2011 | F - Formal Settlement |