Inspection Detail
Inspection: 314166398 - Tomahawk Development
Inspection Information - Office: Baltimore Area Office
Site Address:
Tomahawk Development
3646 Georgia Ave, Nw
Washington, DC 20010
Mailing Address:
10704 Oak Place, Fairfax, VA 22030
Union Status: NonUnion
SIC:1771
NAICS: 238110/Poured Concrete Foundation and Structure Contractors
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 03/04/2010
Emphasis: L:Fall, S:Commercial Constr, S:Fall From Height
Case Closed: 06/17/2010
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 5 | 5 | ||||
| Current Violations | 5 | 5 | ||||
| Initial Penalty | $2,400 | $0 | $0 | $0 | $0 | $2,400 |
| Current Penalty | $1,680 | $0 | $0 | $0 | $0 | $1,680 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260102 A01 | 03/26/2010 | 03/31/2010 | $210 | $300 | $0 | I - Informal Settlement | ||
| 2. | 01002 | Serious | 19260501 C01 | 03/26/2010 | 03/31/2010 | $368 | $525 | $0 | I - Informal Settlement | ||
| 3. | 01003 | Serious | 19260502 B02 | 03/26/2010 | 03/31/2010 | $368 | $525 | $0 | I - Informal Settlement | ||
| 4. | 01004 | Serious | 19260502 B03 | 03/26/2010 | 03/31/2010 | $368 | $525 | $0 | I - Informal Settlement | ||
| 5. | 01005 | Serious | 19261052 C01 II | 03/26/2010 | 03/31/2010 | $368 | $525 | $0 | I - Informal Settlement |