Inspection Detail
Inspection: 314067679 - Rnv Construction
Inspection Information - Office: San Francisco Ro
Site Address:
Rnv Construction
Saipan Office Bridge Capital Office Renovation
Saipan, MP 96950
Mailing Address:
Po Box 504974, Ck, Saipan, MP 96950
Union Status: NonUnion
SIC:1542
NAICS: 236220/Commercial and Institutional Building Construction
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 02/23/2010
Planning Guide: Safety-Construction
Emphasis: L:Progcon, S:Amputations, S:Commercial Constr, S:Electrical, S:Fall From Height, S:Silica, S:Struck-By
Case Closed: 05/10/2016
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 3 | 4 | |||
| Current Violations | 1 | 3 | 4 | |||
| Initial Penalty | $375 | $0 | $0 | $0 | $0 | $375 |
| Current Penalty | $200 | $0 | $0 | $0 | $0 | $200 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Serious | 19260600 A03 I | 04/15/2010 | 06/02/2010 | $200 | $375 | $0 | 05/04/2010 | F - Formal Settlement | |
| 2. | 01001B | Serious | 19260601 B01 | 04/15/2010 | 06/02/2010 | $0 | $0 | $0 | 05/04/2010 | F - Formal Settlement | |
| 3. | 02001 | Other | 19101200 E01 | 04/15/2010 | 06/02/2010 | $0 | $0 | $0 | 05/04/2010 | F - Formal Settlement | |
| 4. | 02002 | Other | 19101200 G01 | 04/15/2010 | 06/02/2010 | $0 | $0 | $0 | 05/04/2010 | F - Formal Settlement | |
| 5. | 02003 | Other | 19101200 H | 04/15/2010 | 06/02/2010 | $0 | $0 | $0 | 05/04/2010 | F - Formal Settlement |