Inspection Detail
Inspection: 313593741 - Serrano Construction & Development
Inspection Information - Office: San Francisco Ro
Site Address:
Serrano Construction & Development
Mt.Santa Rosa Building #72
Yndersen Afb, GU 96929
Mailing Address:
Po Box 20429, Barrigada, GU 96921
Union Status: NonUnion
SIC:1522
NAICS: 236220/Commercial and Institutional Building Construction
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 08/24/2009
Emphasis: L:Progcon, S:Commercial Constr, S:Electrical
Case Closed: 04/28/2011
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 3 | 1 | 4 | |||
| Current Violations | 3 | 1 | 4 | |||
| Initial Penalty | $2,200 | $0 | $0 | $0 | $0 | $2,200 |
| Current Penalty | $1,430 | $0 | $0 | $0 | $0 | $1,430 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Serious | 19101200 E01 | 11/20/2009 | 12/17/2009 | $520 | $800 | $0 | I - Informal Settlement | ||
| 2. | 01001B | Serious | 19101200 E01 I | 11/20/2009 | 12/17/2009 | $0 | $0 | $0 | - | ||
| 3. | 01001C | Serious | 19101200 G01 | 11/20/2009 | 12/17/2009 | $0 | $0 | $0 | - | ||
| 4. | 01002 | Serious | 19260095 A | 11/20/2009 | 11/24/2009 | $390 | $600 | $0 | I - Informal Settlement | ||
| 5. | 01003 | Serious | 19260102 A01 | 11/20/2009 | 11/24/2009 | $520 | $800 | $0 | I - Informal Settlement | ||
| 6. | 02001 | Other | 19260050 D01 | 11/20/2009 | 11/24/2009 | $0 | $0 | $0 | - |
Translate