Inspection Detail
Inspection: 310441126 - J.R. Johnson Dba Cornerstone Construction
Inspection Information - Office: Fort Worth Area Office
Site Address:
J.R. Johnson Dba Cornerstone Construction
2005 N. Main
Cleburne, TX 76033
Mailing Address:
8545 Midpark Rd. #27, Dallas, TX 75240
Union Status: NonUnion
SIC:1741
NAICS: 238140/Masonry Contractors
Inspection Type: Referral
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 07/12/2007
Emphasis: L:Constr6, S:Commercial Constr, S:Fall From Height
Case Closed: 02/11/2016
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Referral | 200715969 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 5 | 7 | 12 | |||
| Current Violations | 5 | 7 | 12 | |||
| Initial Penalty | $9,400 | $0 | $28,000 | $0 | $0 | $37,400 |
| Current Penalty | $9,400 | $0 | $28,000 | $0 | $0 | $37,400 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260100 A | 11/08/2007 | 11/29/2007 | $1,400 | $1,400 | $0 | 01/28/2008 | F - Formal Settlement | |
| 2. | 01002 | Serious | 19260451 A06 | 11/08/2007 | 11/29/2007 | $2,000 | $2,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 3. | 01003 | Serious | 19260451 E09 IV | 11/08/2007 | 11/29/2007 | $2,000 | $2,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 4. | 01004A | Serious | 19260451 G04 I | 11/08/2007 | 11/29/2007 | $2,000 | $2,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 5. | 01004B | Serious | 19260451 G04 IV | 11/08/2007 | 11/29/2007 | $0 | $0 | $0 | 01/28/2008 | F - Formal Settlement | |
| 6. | 01005A | Serious | 19260454 A | 11/08/2007 | 11/27/2007 | $2,000 | $2,000 | $0 | 01/28/2008 | J - ALJ Decision | |
| 7. | 01005B | Serious | 19260454 B | 11/08/2007 | 11/29/2007 | $0 | $0 | $0 | 01/28/2008 | F - Formal Settlement | |
| 8. | 02001 | Repeat | 19260451 B01 I | 11/08/2007 | 11/21/2007 | $4,000 | $4,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 9. | 02002 | Repeat | 19260451 C02 II | 11/08/2007 | 11/21/2007 | $4,000 | $4,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 10. | 02003 | Repeat | 19260451 E01 | 11/08/2007 | 11/21/2007 | $4,000 | $4,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 11. | 02004 | Repeat | 19260451 F03 | 11/08/2007 | 11/21/2007 | $4,000 | $4,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 12. | 02005 | Repeat | 19260451 F07 | 11/08/2007 | 11/21/2007 | $4,000 | $4,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 13. | 02006 | Repeat | 19260451 G01 | 11/08/2007 | 11/21/2007 | $4,000 | $4,000 | $0 | 01/28/2008 | F - Formal Settlement | |
| 14. | 02007 | Repeat | 19260451 H01 | 11/08/2007 | 11/21/2007 | $4,000 | $4,000 | $0 | 01/28/2008 | F - Formal Settlement |