Inspection Detail
Inspection: 307917757 - Tree Equipment Design Inc
Inspection Information - Office: Wilkes Barre Area Office
Site Address:
Tree Equipment Design Inc
1392 West Penn Pike
New Ringgold, PA 17960
Mailing Address:
, , 00000
Union Status: NonUnion
SIC:3523
NAICS: 333111/Farm Machinery and Equipment Manufacturing
Inspection Type: Complaint
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 12/12/2005
Planning Guide: Safety-Manufacturing
Emphasis:
Case Closed: 09/15/2006
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Complaint | 205001100 | Yes | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 5 | 5 | ||||
| Current Violations | 5 | 5 | ||||
| Initial Penalty | $5,200 | $0 | $0 | $0 | $0 | $5,200 |
| Current Penalty | $1,500 | $0 | $0 | $0 | $0 | $1,500 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19100022 A01 | 01/11/2006 | 04/01/2006 | $100 | $600 | $0 | 01/31/2006 | F - Formal Settlement | |
| 2. | 01002 | Serious | 19100037 A03 | 01/11/2006 | 03/01/2006 | $300 | $1,000 | $0 | 01/31/2006 | F - Formal Settlement | |
| 3. | 01003A | Serious | 19100179 J02 III | 01/11/2006 | 03/01/2006 | $150 | $800 | $0 | 01/31/2006 | F - Formal Settlement | |
| 4. | 01003B | Serious | 19100179 J02 IV | 01/11/2006 | 03/01/2006 | $0 | $0 | $0 | 01/31/2006 | F - Formal Settlement | |
| 5. | 01004 | Serious | 19100212 A01 | 01/11/2006 | 04/01/2006 | $150 | $800 | $0 | 01/31/2006 | F - Formal Settlement | |
| 6. | 01005 | Serious | 19100303 B01 III | 01/11/2006 | 04/01/2006 | $800 | $2,000 | $0 | 01/31/2006 | F - Formal Settlement |