Inspection: 306219148 - Engineering & Cycle Co., Inc.

Inspection Information - Office: Atlanta East Area Office

 

Inspection Nr: 306219148
Report ID: 0418100
Date Opened: 03/23/2004

Site Address:
Engineering & Cycle Co., Inc.
Madico Industrial Park
Comer, GA 30629

Mailing Address:
P. O. Box 67, Comer, GA 30629

Union Status: NonUnion

SIC:3545

NAICS: 333515/Cutting Tool and Machine Tool Accessory Manufacturing


Inspection Type: Complaint

Scope: Partial

Advanced Notice: N

Ownership: Private

Safety/Health: Safety

Close Conference: 04/06/2004

Planning Guide: Safety-Manufacturing

Emphasis: N:Amputate, S:Amputations

Case Closed: 08/20/2007


Related Activity
Type Activity Nr Safety Health
Complaint 204290183 Yes
Violation Summary
Violations/Penalties Serious Willful Repeat Other Unclass Total
Initial Violations 13 2 15
Current Violations 13 2 15
Initial Penalty $20,250 $0 $0 $0 $0 $20,250
Current Penalty $12,000 $0 $0 $0 $0 $12,000
FTA Penalty $0 $0 $0 $0 $0 $0

Violation Items
# Citation ID Citaton Type Standard Cited Issuance Date Abatement Due Date Current Penalty Initial Penalty FTA Penalty Contest Latest Event Note
1. 01001 Serious 19100147 C05 IID 07/02/2004 07/29/2004 $900 $1,000 $0 I - Informal Settlement  
2. 01002 Serious 19100151 C 07/02/2004 07/15/2004 $900 $1,000 $0 I - Informal Settlement  
3. 01003 Serious 19100212 A01 07/02/2004 08/14/2004 $1,000 $1,750 $0 I - Informal Settlement  
4. 01004A Serious 19100215 A02 07/02/2004 07/08/2004 $900 $1,000 $0 I - Informal Settlement  
5. 01004B Serious 19100215 A04 07/02/2004 07/09/2004 $0 $0 $0 -  
6. 01004C Serious 19100215 B09 07/02/2004 07/15/2004 $0 $0 $0 -  
7. 01005 Serious 19100242 B 07/02/2004 07/22/2004 $1,000 $2,500 $0 I - Informal Settlement  
8. 01006 Serious 19100253 B04 III 07/02/2004 07/09/2004 $900 $1,250 $0 I - Informal Settlement  
9. 01007 Serious 19100303 B02 07/02/2004 08/14/2004 $900 $2,500 $0 I - Informal Settlement  
10. 01008 Serious 19100303 F 07/02/2004 07/15/2004 $900 $1,250 $0 I - Informal Settlement  
11. 01009 Serious 19100304 F05 VC8 07/02/2004 07/08/2004 $900 $1,000 $0 I - Informal Settlement  
12. 01010 Serious 19100305 A01 I 07/02/2004 07/13/2004 $900 $1,000 $0 I - Informal Settlement  
13. 01011A Serious 19100305 B01 07/02/2004 07/15/2004 $1,000 $2,500 $0 I - Informal Settlement  
14. 01011B Serious 19100305 B02 07/02/2004 07/12/2004 $0 $0 $0 -  
15. 01012 Serious 19100305 G01 IIIA 07/02/2004 07/22/2004 $900 $1,750 $0 I - Informal Settlement  
16. 01013 Serious 19100305 G02 III 07/02/2004 07/22/2004 $900 $1,750 $0 I - Informal Settlement  
17. 02001 Other 19100022 D01 07/02/2004 07/22/2004 $0 $0 $0 -  
18. 02002 Other 19100157 C04 07/02/2004 07/29/2004 $0 $0 $0 -  
Back to Top

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.