Inspection Detail
Inspection: 301916011 - Marta Track Construction, Inc.
Inspection Information - Office: Cleveland Area Office
Site Address:
Marta Track Construction, Inc.
Rta Rehabilitation Project
Cleveland, OH 44119
Mailing Address:
P.O. Box 1509, Washington, PA 15301
Union Status: NonUnion
SIC:1629
NAICS: 0
Inspection Type: Prog Related
Scope: Partial
Advanced Notice: Y
Ownership: Private
Safety/Health: Safety
Close Conference: 05/29/1998
Emphasis:
Case Closed: 09/03/1999
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 4 | 4 | ||||
| Current Violations | 1 | 1 | ||||
| Initial Penalty | $10,000 | $0 | $0 | $0 | $0 | $10,000 |
| Current Penalty | $2,500 | $0 | $0 | $0 | $0 | $2,500 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 5A0001 | 06/02/1998 | 06/05/1998 | $2,500 | $2,500 | $0 | 06/25/1998 | F - Formal Settlement | Citation has been deleted. |
| 2. | 01002 | Serious | 19260020 B02 | 06/02/1998 | 06/05/1998 | $2,500 | $2,500 | $0 | 06/25/1998 | F - Formal Settlement | Citation has been deleted. |
| 3. | 01003 | Serious | 19260021 B02 | 06/02/1998 | 06/05/1998 | $2,500 | $2,500 | $0 | 06/25/1998 | F - Formal Settlement | Citation has been deleted. |
| 4. | 01004 | Serious | 19260550 B02 | 06/02/1998 | 06/05/1998 | $2,500 | $2,500 | $0 | 06/25/1998 | F - Formal Settlement |
Translate