Inspection Detail
Inspection: 2749810 - Portage Construction Co Inc
Inspection Information - Office: Indiana Department Of Labor
Site Address:
Portage Construction Co Inc
Transmission 3703 Grape Road
Mishawaka, IN 46544
Mailing Address:
129 Dixie Way South, South Bend, IN 46637
Union Status: NonUnion
SIC:1751
NAICS: 0
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 08/28/1985
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 10/22/1985
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 3 | 4 | 7 | |||
| Current Violations | 3 | 4 | 7 | |||
| Initial Penalty | $360 | $0 | $0 | $0 | $0 | $360 |
| Current Penalty | $360 | $0 | $0 | $0 | $0 | $360 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260100 A | 09/13/1985 | 08/26/1985 | $120 | $120 | $0 | - | ||
| 2. | 01002A | Serious | 19260400 H01 | 09/13/1985 | 08/26/1985 | $120 | $120 | $0 | - | ||
| 3. | 01002B | Serious | 19260401 C | 09/13/1985 | 08/26/1985 | $0 | $0 | $0 | - | ||
| 4. | 01003A | Serious | 19260451 E04 | 09/13/1985 | 09/18/1985 | $120 | $120 | $0 | - | ||
| 5. | 01003B | Serious | 19260451 E10 | 09/13/1985 | 09/18/1985 | $0 | $0 | $0 | - | ||
| 6. | 02001 | Other | 19260050 F | 09/13/1985 | 08/28/1985 | $0 | $0 | $0 | - | ||
| 7. | 02002 | Other | 19260150 C01 I | 09/13/1985 | 08/28/1985 | $0 | $0 | $0 | - | ||
| 8. | 02003 | Other | 19260252 C | 09/13/1985 | 08/28/1985 | $0 | $0 | $0 | - | ||
| 9. | 02004 | Other | 19260402 C01 | 09/13/1985 | 08/27/1985 | $0 | $0 | $0 | - |