Inspection Detail
Inspection: 17825886 - Process Engineers And Constructors, Inc.
Inspection Information - Office: Springfield Area Office
Site Address:
Process Engineers And Constructors, Inc.
Enron/Milford Power Project 108 National St.
Milford, MA 01757
Mailing Address:
159 Knight St., Warwick, RI 02886
Union Status: Union
SIC:1711
NAICS: 0
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 01/19/1993
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 02/16/1993
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | ||||
| Current Violations | 2 | 2 | ||||
| Initial Penalty | $900 | $0 | $0 | $0 | $0 | $900 |
| Current Penalty | $450 | $0 | $0 | $0 | $0 | $450 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260059 E04 | 02/01/1993 | 02/04/1993 | $0 | $450 | $0 | I - Informal Settlement | ||
| 2. | 01002 | Serious | 19260350 D02 | 02/01/1993 | 02/04/1993 | $450 | $450 | $0 | - |