Inspection Detail
Inspection: 1264781.015 - Vmc Construction, Llc
Inspection Information - Office: Atlanta East Area Office
Site Address:
Vmc Construction, Llc
4130 Oxcliffe Grove
Suwanee, GA 30024
Mailing Address:
5726 Harmony Point Drive, Lilburn, GA 30047
Union Status: NonUnion
SIC:
NAICS: 238130/Framing Contractors
Inspection Type: Planned
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 08/11/2017
Emphasis: P:Fall, L:Fall
Case Closed: 09/13/2020
Type | Activity Nr | Safety | Health |
---|---|---|---|
Inspection | 1254167 | Yes | |
Inspection | 1254139 | Yes |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 3 | 4 | 7 | |||
Current Violations | 3 | 4 | 7 | |||
Initial Penalty | $12,195 | $0 | $87,804 | $0 | $0 | $99,999 |
Current Penalty | $7,000 | $0 | $51,000 | $0 | $0 | $58,000 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 19260020 B01 | 01/23/2018 | 02/16/2018 | $2,500 | $5,691 | $0 | I - Informal Settlement | ||
2. | 01002 | Serious | 19260025 A | 01/23/2018 | 02/16/2018 | $2,000 | $2,439 | $0 | I - Informal Settlement | ||
3. | 01003 | Serious | 19261425 C03 | 01/23/2018 | 02/16/2018 | $2,500 | $4,065 | $0 | I - Informal Settlement | ||
4. | 02001 | Repeat | 19260100 A | 01/23/2018 | 02/16/2018 | $7,000 | $8,130 | $0 | I - Informal Settlement | ||
5. | 02002 | Repeat | 19260102 A01 | 01/23/2018 | 02/16/2018 | $7,000 | $11,382 | $0 | I - Informal Settlement | ||
6. | 02003 | Repeat | 19260501 B13 | 01/23/2018 | 02/16/2018 | $30,000 | $56,910 | $0 | I - Informal Settlement | ||
7. | 02004 | Repeat | 19261053 B01 | 01/23/2018 | 02/16/2018 | $7,000 | $11,382 | $0 | I - Informal Settlement |