Inspection Detail
Inspection: 12325098 - Foster Wheeler Energy Corporat
Inspection Information - Office: Charleston Area Office
Site Address:
Foster Wheeler Energy Corporat
Pleasants Power Station Route
Willow Island, WV 26190
Mailing Address:
, , 00000
Union Status: Union
SIC:1629
NAICS: 0
Inspection Type: Accident
Scope: Partial
Advanced Notice:
Ownership:
Safety/Health: Safety
Close Conference: 06/15/1978
Planning Guide: Safety-Construction
Emphasis:
Case Closed: 06/24/1980
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Accident | 350034021 |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 3 | 5 | |||
| Current Violations | 2 | 3 | 5 | |||
| Initial Penalty | $1,700 | $19,600 | $0 | $0 | $0 | $21,300 |
| Current Penalty | $1,200 | $18,800 | $0 | $0 | $0 | $20,000 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260021 B02 | 07/03/1978 | 07/06/1978 | $400 | $900 | $0 | 07/15/1978 | W - Empr Withdrew | |
| 2. | 01002 | Serious | 19260552 B01 I | 07/03/1978 | 07/06/1978 | $800 | $800 | $0 | 07/15/1978 | W - Empr Withdrew | |
| 3. | 02001A | Willful | 19260451 E04 | 07/03/1978 | 07/06/1978 | $800 | $1,600 | $0 | 07/15/1978 | W - Empr Withdrew | |
| 4. | 02001B | Willful | 19260451 E08 | 07/03/1978 | 07/06/1978 | $0 | $0 | $0 | 07/15/1978 | - | |
| 5. | 02001C | Willful | 19260451 E10 | 07/03/1978 | 07/06/1978 | $0 | $0 | $0 | 07/15/1978 | - | |
| 6. | 02002 | Willful | 19260500 D01 | 07/03/1978 | 07/06/1978 | $9,000 | $9,000 | $0 | 07/15/1978 | W - Empr Withdrew | |
| 7. | 02003 | Willful | 19260750 B01 II | 07/03/1978 | 07/06/1978 | $9,000 | $9,000 | $0 | 07/15/1978 | W - Empr Withdrew |