Inspection Detail
Inspection: 1160123.015 - Wa317941273 - Harkey Construction And Development Inc
Inspection Information - Office: Dosh Yakima Service Location, Yakima, Wa
Site Address:
Wa317941273 - Harkey Construction And Development Inc
122 Granite Ridge Dr.
Chelan, WA 98816
Mailing Address:
Po Box 1504, Chelan, WA 98816
Union Status: NonUnion
SIC:
NAICS: 238130/Framing Contractors
Inspection Type: Planned
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 06/08/2016
Emphasis: P:Constr, S:Constr
Case Closed: 02/22/2017
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 4 | 3 | 7 | |||
| Current Violations | 4 | 3 | 7 | |||
| Initial Penalty | $3,600 | $0 | $0 | $300 | $0 | $3,900 |
| Current Penalty | $3,600 | $0 | $0 | $300 | $0 | $3,900 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citation Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 296-155-657(1)(A) | 09/02/2016 | 06/08/2016 | $900 | $900 | $0 | Z - Issued | ||
| 2. | 01002 | Serious | 296-155-655(11)(A) | 09/02/2016 | 10/05/2016 | $900 | $900 | $0 | Z - Issued | ||
| 3. | 01003 | Serious | 296-155-205(3) | 09/02/2016 | 06/08/2016 | $900 | $900 | $0 | Z - Issued | ||
| 4. | 01004 | Serious | 296-155-24607(3) | 09/02/2016 | 06/08/2016 | $900 | $900 | $0 | Z - Issued | ||
| 5. | 02001 | Other | 296-155-110(9)(A) | 09/02/2016 | 09/10/2016 | $0 | $0 | $0 | Z - Issued | ||
| 6. | 02002 | Other | 296-155-120(1) | 09/02/2016 | 10/05/2016 | $0 | $0 | $0 | Z - Issued | ||
| 7. | 02003A | Other | 296-27-02105(1)(D) | 09/02/2016 | 06/08/2016 | $300 | $300 | $0 | Z - Issued | ||
| 8. | 02003B | Other | 296-27-01101(1) | 09/02/2016 | 06/08/2016 | $0 | $0 | $0 | Z - Issued |
Translate