Inspection Detail
Inspection: 1076915.015 - Fabco Steel Fabrication Inc
Inspection Information - Office: San Bernardino District Office
Site Address:
Fabco Steel Fabrication Inc
14688 San Bernardino Avenue
Fontana, CA 92335
Mailing Address:
Po Box 8636, Alta Loma, CA 91701
Union Status: NonUnion
SIC:
NAICS: 332710/Machine Shops
Inspection Type: Accident
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 12/29/2015
Emphasis:
Case Closed: 06/14/2016
Type | Activity Nr | Safety | Health |
---|---|---|---|
Accident | 998261 |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 2 | 4 | 6 | |||
Current Violations | 2 | 4 | 6 | |||
Initial Penalty | $36,000 | $0 | $0 | $7,055 | $0 | $43,055 |
Current Penalty | $8,660 | $0 | $0 | $7,055 | $0 | $15,715 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Other | 342(A) | 12/29/2015 | 01/19/2016 | $5,000 | $5,000 | $0 | 01/21/2016 | F - Formal Settlement | |
2. | 01002 | Other | 3314(L) | 12/29/2015 | 01/19/2016 | $685 | $685 | $0 | 01/21/2016 | F - Formal Settlement | |
3. | 01003 | Other | 3328(B) | 12/29/2015 | 01/19/2016 | $685 | $685 | $0 | 01/21/2016 | F - Formal Settlement | |
4. | 01004 | Other | 3942(A) | 12/29/2015 | 01/19/2016 | $685 | $685 | $0 | 01/21/2016 | F - Formal Settlement | |
5. | 02001 | Serious | 3314(C) | 12/29/2015 | 01/19/2016 | $6,185 | $18,000 | $0 | 01/21/2016 | F - Formal Settlement | |
6. | 03001 | Serious | 4070(A) | 12/29/2015 | $2,475 | $18,000 | $0 | 01/21/2016 | F - Formal Settlement |