Inspection Detail
Inspection: 1066800.015 - K&F Construction, Inc.
Inspection Information - Office: Charleston Area Office
Site Address:
K&F Construction, Inc.
Suncrest Village 100 Townhouse Way
Morgantown, WV 26505
Mailing Address:
Po Box 6013, Martinsburg, WV 25402
Union Status: NonUnion
SIC:
NAICS: 238130/Framing Contractors
Inspection Type: FollowUp
Scope: Partial
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 05/27/2015
Emphasis: P:Fall, L:Fall
Case Closed: 11/21/2017
Type | Activity Nr | Safety | Health |
---|---|---|---|
Inspection | 1015126 | Yes |
Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
---|---|---|---|---|---|---|
Initial Violations | 2 | 1 | 3 | |||
Current Violations | 2 | 1 | 3 | |||
Initial Penalty | $5,720 | $38,500 | $0 | $0 | $0 | $44,220 |
Current Penalty | $3,432 | $23,100 | $0 | $0 | $0 | $26,532 |
FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
# | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
---|---|---|---|---|---|---|---|---|---|---|---|
1. | 01001 | Serious | 19260025 A | 09/18/2015 | 09/28/2015 | $1,584 | $2,640 | $0 | 10/15/2015 | F - Formal Settlement | |
2. | 01002 | Serious | 19260503 A01 | 09/18/2015 | 09/30/2015 | $1,848 | $3,080 | $0 | 10/15/2015 | F - Formal Settlement | |
3. | 02001 | Willful | 19260501 B13 | 09/18/2015 | 09/28/2015 | $23,100 | $38,500 | $0 | 10/15/2015 | F - Formal Settlement |