Close Conference: 07/16/1990
Planning Guide: Safety-Construction
Emphasis: N:Trench
Case Closed: 09/20/1991
| Type | Activity Nr | Safety | Health |
|---|---|---|---|
| Referral | 900989435 | Yes |
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 13 | 1 | 1 | 15 | ||
| Current Violations | 13 | 1 | 1 | 15 | ||
| Initial Penalty | $5,700 | $8,000 | $0 | $0 | $0 | $13,700 |
| Current Penalty | $2,000 | $2,800 | $0 | $0 | $0 | $4,800 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260020 B01 | 07/18/1990 | 08/20/1990 | $210 | $600 | $0 | 08/08/1990 | F - Formal Settlement | |
| 2. | 01002 | Serious | 19260021 B02 | 07/18/1990 | 08/20/1990 | $210 | $600 | $0 | 08/08/1990 | F - Formal Settlement | |
| 3. | 01003A | Serious | 19260054 B | 07/18/1990 | 08/20/1990 | $70 | $200 | $0 | 08/08/1990 | F - Formal Settlement | |
| 4. | 01003B | Serious | 19260054 D | 07/18/1990 | 07/27/1990 | $0 | $0 | $0 | 08/08/1990 | F - Formal Settlement | |
| 5. | 01004 | Serious | 19260059 E01 | 07/18/1990 | 08/20/1990 | $70 | $200 | $0 | 08/08/1990 | F - Formal Settlement | |
| 6. | 01005 | Serious | 19260059 F05 I | 07/18/1990 | 07/27/1990 | $70 | $200 | $0 | 08/08/1990 | F - Formal Settlement | |
| 7. | 01006 | Serious | 19260059 G08 | 07/18/1990 | 08/20/1990 | $70 | $200 | $0 | 08/08/1990 | F - Formal Settlement | |
| 8. | 01007 | Serious | 19260059 H | 07/18/1990 | 08/20/1990 | $70 | $200 | $0 | 08/08/1990 | F - Formal Settlement | |
| 9. | 01008 | Serious | 19260651 D | 07/18/1990 | 07/27/1990 | $70 | $200 | $0 | 08/08/1990 | F - Formal Settlement | |
| 10. | 01009 | Serious | 19260651 J02 | 07/18/1990 | 07/27/1990 | $280 | $800 | $0 | 08/08/1990 | F - Formal Settlement | |
| 11. | 01010 | Serious | 19260651 K01 | 07/18/1990 | 07/27/1990 | $280 | $800 | $0 | 08/08/1990 | F - Formal Settlement | |
| 12. | 01011 | Serious | 19260652 A01 | 07/18/1990 | 07/27/1990 | $210 | $600 | $0 | 08/08/1990 | F - Formal Settlement | |
| 13. | 01012 | Serious | 19260652 G01 III | 07/18/1990 | 07/27/1990 | $250 | $700 | $0 | 08/08/1990 | F - Formal Settlement | |
| 14. | 01013 | Serious | 19260652 G01 IV | 07/18/1990 | 07/27/1990 | $140 | $400 | $0 | 08/08/1990 | F - Formal Settlement | |
| 15. | 02001 | Willful | 19260652 A01 | 07/18/1990 | 07/27/1990 | $2,800 | $8,000 | $0 | 08/08/1990 | F - Formal Settlement | |
| 16. | 03001 | Other | 19260152 G09 | 07/18/1990 | 07/27/1990 | $0 | $0 | $0 | 08/08/1990 | F - Formal Settlement |