Inspection: 10209153 - Anastasi Brothers Corp
Inspection Information - Office: Boston South Area Office
Site Address:
Anastasi Brothers Corp
Masco Power Plant Project
Boston, MA 02215
Mailing Address:
, , 00000
Union Status: Union
SIC:1741
NAICS: 0
Inspection Type: Planned
Scope: Complete
Advanced Notice:
Ownership:
Safety/Health: Health
Close Conference: 02/05/1979
Planning Guide: Health-Construction
Emphasis:
Case Closed: 05/22/1981
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 1 | 1 | ||||
| Current Violations | 1 | 1 | ||||
| Initial Penalty | $720 | $0 | $0 | $0 | $0 | $720 |
| Current Penalty | $720 | $0 | $0 | $0 | $0 | $720 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citaton Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001A | Serious | 19100095 A | 02/14/1979 | 02/17/1979 | $720 | $720 | $0 | 03/15/1979 | - | |
| 2. | 01001B | Serious | 19100095 B01 | 02/14/1979 | 06/18/1979 | $0 | $0 | $0 | 03/15/1979 | - | |
| 3. | 01001C | Serious | 19100095 B03 | 02/14/1979 | 05/14/1979 | $0 | $0 | $0 | 03/15/1979 | - |