Inspection Detail
Inspection: 100549278 - Spear Pipeline Construction
Inspection Information - Office: Region 09; San Francisco
Site Address:
Spear Pipeline Construction
12360 Baseline Road
Rancho Cucamonga, CA 91730
Mailing Address:
120 North Mcpherson, Orange, CA 92669
Union Status: NonUnion
SIC:1623
NAICS: 0
Inspection Type: Planned
Scope: Complete
Advanced Notice: N
Ownership: Private
Safety/Health: Safety
Close Conference: 12/21/1987
Planning Guide: Safety-Construction
Emphasis: N:Trench
Case Closed: 01/13/1988
| Violations/Penalties | Serious | Willful | Repeat | Other | Unclass | Total |
|---|---|---|---|---|---|---|
| Initial Violations | 2 | 2 | 4 | |||
| Current Violations | 2 | 2 | 4 | |||
| Initial Penalty | $480 | $0 | $0 | $0 | $0 | $480 |
| Current Penalty | $480 | $0 | $0 | $0 | $0 | $480 |
| FTA Penalty | $0 | $0 | $0 | $0 | $0 | $0 |
| # | Citation ID | Citation Type | Standard Cited | Issuance Date | Abatement Due Date | Current Penalty | Initial Penalty | FTA Penalty | Contest | Latest Event | Note |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 1. | 01001 | Serious | 19260651 C | 12/30/1987 | 01/04/1988 | $240 | $240 | $0 | - | ||
| 2. | 01002 | Serious | 19260652 E | 12/30/1987 | 01/04/1988 | $240 | $240 | $0 | - | ||
| 3. | 02001 | Other | 19030002 A01 | 12/30/1987 | 01/02/1988 | $0 | $0 | $0 | - | ||
| 4. | 02002 | Other | 19260450 A10 | 12/30/1987 | 01/04/1988 | $0 | $0 | $0 | - |
Translate