TEXT VERSION OF SLIDE:
Title: BEFORE/AFTER
Type: Text Slide with Images
Content:
COST: $51,000
COST RECOVERY TIME: 8-12 months
BENEFITS: Eliminated strain from repetition, vibration and poor posture, increased productivity,
increased scrap metal recovery for resale, reduced silica exposure.
| Lump Crusher |
Position |
Frequency |
Twisting |
Grasp |
Opinion |
Total |
|
Weight |
Deg |
Freq |
Grip |
Foot |
| Before |
4 |
4 |
8 |
4 |
0 |
4 |
4 |
6 |
34 |
| After |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
[Includes two photos; one of a worker using a jack hammer to break up air set core from casting,
and one of a core lump crusher]
|