Slide 34

    TEXT VERSION OF SLIDE:

    Title: MILLER PARK STADIUM -- RESULTS
    Type: Text Slide with Two Lists
    Content:
     
    Original budget
    $ 322M
    Final Cost: $ 850M+?
    – $413.9M (construction)
    – $100M (repairs)
    – $27-99M (jury awards)
    – $330.8M (interest on bonds)

    Litigation is ongoing with over a Hundred Million Dollars in claims still unresolved.

    [Includes clipart image of stadium.]

    Speaker Notes:

    The original budget for Miller Park was $322M --

    Due to the crane collapse -- the final cost, which is still unknown, was $413.9M for construction, $100M for repairs from the collapse (insured). In addition -- the insured will have between $27M and $99M for jury award to beneficiaries. Also, the interest on the bonds turned out to be more than the original construction cost.


 
Back to Top Back to Top www.osha.gov www.dol.gov

Contact Us | Freedom of Information Act | Customer Survey
Privacy and Security Statement | Disclaimers
Occupational Safety & Health Administration
200 Constitution Avenue, NW
Washington, DC 20210