US Dept of Labor

Occupational Safety & Health AdministrationWe Can Help

Violation Detail

Standard Cited: 5A0001 OSH Act General Duty Paragraph

Violation Items

Nr: 314737206 Citation: 01017A Issuance: 01/31/2011 ReportingID: 0627100

Viol Type:Serious NrInstances:10 Contest Date:
Abatement Date:09/04/2011 X Nr Exposed: Final Order:
Initial Penalty: $5,000.00 REC:C Emphasis:
Current Penalty: $5,000.00 Gravity:10 Haz Category:LOCKOUT

Penalty and Failure to Abate Event History
Type Event Date Penalty Abatement Type FTA Insp
Penalty Z: Issued 01/31/2011 $5,000.00 03/04/2011 Serious  
Penalty I: Informal Settlement 02/22/2011 $5,000.00 09/04/2011 Serious  

Text For Citation: 01 Item/Group: 017A Hazard: LOCKOUT

Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to: At the Spiral Plant on or about January 19, 2011 and prior thereto, employees walking through and working in the pipe conveyor/transfer lines were exposed to the hazard of being struck by or caught between moving pipes in instances such as but not limited to the following: a.Final Finish at the south side of the skid east of OD Grinding b.Final Finish at the north side of the skid east of OD Grinding c.Final Finish at the north and south conveyor/transfer line south of the Quality Control work platform d.Beveling at the north and south conveyor/transfer line north of the Quality Control work platform e.Pre-Visual at the north and south conveyor/transfer line south of the pre-Visual Platform f.Pre-Visual at the south side of the skid west of the Pre-Visual Platform g.Skelp Plasma at he north and south conveyor/transfer line h.Stencil Area at the north and south conveyor/transfer line i.Beveling Area at the north and south conveyor/transfer line west of the Beveler and east of the exit door j.Final Finish at the OD Grinding platform Among other means, the following are feasible and acceptable methods to correct this hazard: 1.Install stairs and a walkway over the pipe conveyor/transfer lines. 2.Restrict Access to the pipe conveyor/transfer lines using guarding. 3.Develop, implement and require the use of lockout while employees are performing work when they are in the pipe conveyor/transfer lines or on platforms in the travel path of pipes.

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.