Standard Cited: 5A0001 OSH Act General Duty Paragraph

This violation item has been deleted.

Violation Items

Nr: 311912067 Citation: 01001 Issuance: 10/14/2009 ReportingID: 0830500

Viol Type:Serious NrInstances:2 Contest Date:11/02/2009
Abatement Date:11/03/2009 Nr Exposed:12 Final Order:09/30/2010
Initial Penalty: $2,000.00 REC: Emphasis:
Current Penalty: $2,000.00 Gravity:02 Haz Category:STRUCK BY

Penalty and Failure to Abate Event History
Type Event Date Penalty Abatement Type FTA Insp
Penalty Z: Issued 10/14/2009 $2,000.00 11/03/2009 Serious  
Penalty F: Formal Settlement 09/30/2010 $2,000.00 11/03/2009 Serious  

Text For Citation: 01 Item/Group: 001 Hazard: STRUCK BY

Section 5(a)(1) of the Occupational Safety and Health Act of 1970: The employer did not furnish employment and a place of employment which were free from recognized hazards that were causing or likely to cause death or serious physical harm to employees in that employees were exposed to the hazard of being "struck by" pressurized lines: a) Nabors Drilling USA, Rig 573, Parachute, CO: On and prior to 4/30/2009, 2-two inch rigid gas lines having pressure readings between 2650 and 3850 PSI were not secured to prevent movement in the event of failure. b) On and prior to 4/30/2009, the safety clamp on the 4 inch flexible high pressure mud line going toward the drilling rig was improperly installed. The safety clamp was attached to the rigid steel coupling at the end of the flexible hose. c) On and prior to 4/30/2009, the safety clamp on the high pressure assembly located in the "mud pump" house was improperly installed. The safety clamp was attached to the rigid steel coupling at the end of the flexible hose. Among other methods, one feasible and acceptable abatement method to correct these hazards would be a) stake or place weighted objects over appropriate sections of rigid gas lines and b,c) install safety clamps in accordance with the hose manufacturer markings found on the hose assembly. Typically these markings are placed 8-12 inches inboard of the rigid steel coupling. Abatement Note: Abatement certification is required for this item (See enclosed "Sample Abatement-Certification Letter").-Certification

Thank You for Visiting Our Website

You are exiting the Department of Labor's Web server.

The Department of Labor does not endorse, takes no responsibility for, and exercises no control over the linked organization or its views, or contents, nor does it vouch for the accuracy or accessibility of the information contained on the destination server. The Department of Labor also cannot authorize the use of copyrighted materials contained in linked Web sites. Users must request such authorization from the sponsor of the linked Web site. Thank you for visiting our site. Please click the button below to continue.