Inspection Detail
Case Status: PENDING ABATEMENT OF VIOLATIONS |
Note: The following inspection has not been indicated as closed. Please be aware that the information shown may change, e.g. violations may be added or deleted. For open cases, in which a citation has been issued, the citation information may not be available for 5 days following receipt by the employer for Federal inspections or for 30 days following receipt by the employer for State inspections.
Inspection Information - Office: Oklahoma City | ||||
---|---|---|---|---|
Nr: 1416788.015 | Report ID: 0627700 | Open Date: 07/12/2019 | ||
K & M Highline Services | ||||
Cr 1550 And Cr 2990 Lindsay, OK 73052 | Union Status: NonUnion | |||
SIC: | ||||
NAICS: 237130/Power and Communication Line and Related Structures Construction | ||||
Mailing: 700 Ne 63rd Street, Oklahoma City, OK 73105 | ||||
Inspection Type: | Fat/Cat | |||
Scope: | Partial | Advanced Notice: | N | |
Ownership: | Private | |||
Safety/Health: | Safety | Close Conference: | 07/17/2019 | |
Close Case: | ||||
Related Activity: | Type | ID | Safety | Health |
Accident | 1474802 |
Case Status: PENDING ABATEMENT OF VIOLATIONS |
Violation Summary | ||||||
---|---|---|---|---|---|---|
Serious | Willful | Repeat | Other | Unclass | Total | |
Initial Violations | 3 | 3 | ||||
Current Violations | 3 | 3 | ||||
Initial Penalty | $37,128 | $0 | $0 | $0 | $0 | $37,128 |
Current Penalty | $16,710 | $0 | $0 | $0 | $0 | $16,710 |
FTA Amount | $0 | $0 | $0 | $0 | $0 | $0 |
Violation Items | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
# | ID | Type | Standard | Issuance | Abate | Curr$ | Init$ | Fta$ | Contest | LastEvent | |
1. | 01001A | Serious | 19260950 B02 IV | 12/20/2019 | 02/09/2020 | $5,570 | $9,282 | $0 | I - Informal Settlement | ||
2. | 01001B | Serious | 19260950 B02 V | 12/20/2019 | 02/09/2020 | $0 | $0 | $0 | I - Informal Settlement | ||
3. | 01001C | Serious | 19260960 C01 III B | 12/20/2019 | 02/09/2020 | $0 | $9,282 | $0 | I - Informal Settlement | ||
4. | 01002 | Serious | 19260952 A02 | 12/20/2019 | 02/09/2020 | $5,570 | $9,282 | $0 | I - Informal Settlement | ||
5. | 01004 | Serious | 19260960 D01 | 12/20/2019 | 02/09/2020 | $5,570 | $9,282 | $0 | I - Informal Settlement |
Accident Investigation Summary | ||||||
Summary Nr: 118136.015 | Event: 07/11/2019 | Employee Working On Power Line Is Electrocuted | ||||
At 8:30 a.m. on July 11, 2019, Employee #1 was installing an electrical pole and tapping into a 144-kilovolt power line to provide power to an oil well. He contacted an energized power line and was electrocuted. | ||||||
Keywords: power line worker, power lines, electrocuted, electrical work, elec utility work, construction | ||||||
Inspection | Degree | Nature | Occupation | |||
---|---|---|---|---|---|---|
1 | 1416788.015 | Fatality | Electric Shock |