Inspection Detail
Case Status: VIOLATIONS UNDER CONTEST |
Note: The following inspection has not been indicated as closed. Please be aware that the information shown may change, e.g. violations may be added or deleted. For open cases, in which a citation has been issued, the citation information may not be available for 5 days following receipt by the employer for Federal inspections or for 30 days following receipt by the employer for State inspections.
Inspection Information - Office: Ca Foster City District Office | ||||
---|---|---|---|---|
Nr: 1333964.015 | Report ID: 0950613 | Open Date: 07/27/2018 | ||
Platinum Pipeline, Inc. | ||||
1 Martin Street Daly City, CA 94014 | Union Status: NonUnion | |||
SIC: | ||||
NAICS: 237110/Water and Sewer Line and Related Structures Construction | ||||
Mailing: 357 Stealth Court, P.O. Box 1170, Livermore, CA 94551 | ||||
Inspection Type: | Fat/Cat | |||
Scope: | Partial | Advanced Notice: | N | |
Ownership: | Private | |||
Safety/Health: | Safety | Close Conference: | 01/25/2019 | |
Close Case: | ||||
Related Activity: | Type | ID | Safety | Health |
Accident | 1364239 |
Case Status: VIOLATIONS UNDER CONTEST |
Violation Summary | ||||||
---|---|---|---|---|---|---|
Serious | Willful | Repeat | Other | Unclass | Total | |
Initial Violations | 5 | 2 | 3 | 10 | ||
Current Violations | 5 | 2 | 3 | 10 | ||
Initial Penalty | $23,625 | $216,000 | $0 | $2,975 | $0 | $242,600 |
Current Penalty | $23,625 | $216,000 | $0 | $2,975 | $0 | $242,600 |
FTA Amount | $0 | $0 | $0 | $0 | $0 | $0 |
Violation Items | |||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|
# | ID | Type | Standard | Issuance | Abate | Curr$ | Init$ | Fta$ | Contest | LastEvent | |
1. | 01001 | Other | 1509(A) | 01/25/2019 | 02/13/2019 | $875 | $875 | $0 | 02/22/2019 | - | |
2. | 01002 | Other | 3395(I) | 01/25/2019 | 02/13/2019 | $1,050 | $1,050 | $0 | 02/22/2019 | - | |
3. | 01003 | Other | 3395(H)(1) | 01/25/2019 | 02/13/2019 | $1,050 | $1,050 | $0 | 02/22/2019 | - | |
4. | 02001 | Serious | 1541(B)(1)(D) | 01/25/2019 | $3,150 | $3,150 | $0 | 02/22/2019 | - | ||
5. | 03001 | Serious | 1541(I)(1) | 01/25/2019 | $4,725 | $4,725 | $0 | 02/22/2019 | - | ||
6. | 04001 | Serious | 1541(J)(2) | 01/25/2019 | $6,300 | $6,300 | $0 | 02/22/2019 | - | ||
7. | 05001 | Serious | 15410001 B | 01/25/2019 | $6,300 | $6,300 | $0 | 02/22/2019 | - | ||
8. | 06001 | Serious | 15410001 F | 01/25/2019 | $3,150 | $3,150 | $0 | 02/22/2019 | - | ||
9. | 07001 | Willful | 1541(K)(2) | 01/25/2019 | $108,000 | $108,000 | $0 | 02/22/2019 | - | ||
10. | 08001 | Willful | 15410001 A01 | 01/25/2019 | $108,000 | $108,000 | $0 | 02/22/2019 | - |
Accident Investigation Summary | ||||||
Summary Nr: 107783.015 | Event: 07/27/2018 | Employee Is Killed In Trench Collapse | ||||
At 11:30 a.m. on July 27, 2018, Employee #1 was preparing the pipe placement in a 14 foot deep and 10 foot wide trench. The trench walls were not shored. The soil collapsed into the trench, pinning and killing the employee. | ||||||
Keywords: pinned, trench, shoring, cave-in, collapse, unstable soil, pipe | ||||||
Inspection | Degree | Nature | Occupation | |||
---|---|---|---|---|---|---|
1 | 1333964.015 | Fatality | Other | Laborers, except construction |