Violation Detail
Standard Cited: 19260651 J02 Specific Excavation Requirements.
Inspection Nr: 998397.015
Citation: 01002A
Citation Type: Serious
Abatement Date: 3
Initial Penalty: $2,800.00
Current Penalty: $1,960.00
Issuance Date: 03/11/2015
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC): C
Gravity: 10
Report ID: 0830300
Contest Date:
Final Order: 04/03/2015
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 04/03/2015 | $1,960.00 | Serious | ||
| Penalty | Z: Issued | 03/11/2015 | $2,800.00 | Serious |
Text For Citation: 01 Item/Group: 002A Hazard:
29 CFR 1926.651(j)(2): Employees were not protected from excavated or other materials or equipment that could pose a hazard by falling or rolling into excavations, or by a combination of both if necessary: (a) On or about October 1, 2014, for employees exposed to cave-in hazards while installing a water main from within a trench that measured approximately 9 feet in depth at the 15th Street West project located near the intersection of 21st Street West and 113th Avenue SW in Dickinson, North Dakota.
Translate