Violation Detail
Standard Cited: 19100253 E01 Oxygen-fuel gas welding and cutting.
Inspection Nr: 979470.015
Citation: 03004
Citation Type: Other
Abatement Date: 1
Initial Penalty: $0.00
Current Penalty: $0.00
Issuance Date: 12/01/2014
Nr Instances: 1
Nr Exposed: 2
Related Event Code (REC):
Gravity:
Report ID: 0419400
Contest Date:
Final Order: 01/02/2015
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | I: Informal Settlement | 01/02/2015 | $0.00 | Other | ||
| Penalty | Z: Issued | 12/01/2014 | $0.00 | Other |
Text For Citation: 03 Item/Group: 004 Hazard:
29 CFR 1910.253(e)(1): Equipment was not installed and used only in the service for which it was approved and as recommended by the manufacturer. (a) Heater Treater Shop - On or about June 17, 2014 the regulator gauges were broken on Cart 1, Acetylene side and on Cart 2 Oxygen side.