Violation Detail
Standard Cited: 19100303 F02 General.
Inspection Nr: 930829.015
Citation: 01017
Citation Type: Serious
Abatement Date: 03/11/2014 2
Initial Penalty: $4,400.00
Current Penalty: $4,400.00
Issuance Date: 02/12/2014
Nr Instances: 1
Nr Exposed: 3
Related Event Code (REC):
Gravity: 5
Report ID: 0419700
Contest Date: 03/05/2014
Final Order: 07/10/2015
Emphasis:
| Type | Latest Event | Event Date | Penalty | Abatement Due Date | Citation Type | Failure to Abate Inspection |
|---|---|---|---|---|---|---|
| Penalty | F: Formal Settlement | 07/10/2015 | $4,400.00 | 03/11/2014 | Serious | |
| Penalty | C: Contested | 12/19/2014 | $4,400.00 | 03/11/2014 | Serious | |
| Penalty | Z: Issued | 02/12/2014 | $4,400.00 | 03/11/2014 | Serious |
Text For Citation: 01 Item/Group: 017 Hazard:
29 CFR 1910.303(f)(2): Each service, feeder, and branch circuit, at its disconnecting means or overcurrent device, was not legibly marked to indicate its purpose, nor located and arranged so the purpose was evident: a. On or about August 16, 2013, in the MEP-3 control room, breaker panel L-3's breaker bank was not legibly marked to indicate its purpose.